Introduction

Voluntary Alignment quarters are slightly shifted from calendar quarters; specifically, they are tied to submission dates. For example:

  • Q1: Submission day is 2/15, so the quarter runs from 10/24 the prior year to 2/15

  • Q2: Submission day is 5/15, so the quarter runs from 2/16 to 5/15

  • Q3: Submission day is 8/15, so the quarter runs from 5/16 to 8/15

  • Q4: Submission day is ~11/1, so the quarter runs from 8/16 to 11/1. Unlike the first three quarters, the Q4 submission window is usually shorter and varies based on implementation periods, holidays, etc.

We are currently only including Voluntary Alignment and Beneficiary Notification Letter activities on the calendar, but will shortly also include relevant dates for HEDR Surveys.

Tentative Calendar

Week Key Activities 23Q4 24Q1 24Q2 24Q3
0 Start of new quarter 8/16 10/24 2/16 5/16
1 Send Beneficiary Notification Letters (BNLs) to the calendar quarter's new alignments 8/23 11/10 TBD 5/22
2 Last push for new & updated patient lists before quarterly campaign 8/28 12/20 2/26 5/27
3 Campaigns launch for ACOs ending in (0,3,6,9) 9/4 11/30 & 12/27 3/11 6/3
4 Campaigns launch for ACOs ending in (1,4,7) 9/11 11/30 & 12/27 3/18 6/10
5 Campaigns launch for ACOs ending in (2,5,8) 9/18 11/30 & 12/27 3/25 6/17
6 Catch-up campaigns for updated patient lists N/A 1/10 3/25 6/24
... ... ... ... ... ...
10 Upload 4i Files (BAR, SVA Response File, ACO Participants list) 10/23 1/22 4/22 7/22
11 Complete SVAs Awaiting Information 10/13 2/10 5/10 8/10
12 CMS Submission Day 10/23 2/15 5/15 8/15